What is a logframe?
This document sets out the suggested Steps for developing a Local Action Plan within the context of an URBACT 2 Thematic Network. Experience of a range of strategies and action plans suggests that a number of steps need to be taken in a systematic way for Local Action Plans to be successful. What is set out below is a comprehensive approach to Local Action Plan within the context of URBACT 2. Because of pressures in the real world it is rarely possible to pursue all stages in the detail that is needed. Time is frequently the main enemy, because of a real or perceived need to get into the implementation stage and stop being just a talking shop.
The Planning Cycle
The Planning Cycle (also known as the project or programme cycle depending on the context)brings together all aspects of planning into a coherent, unified process. By planning within this structure, you will help to ensure that your plans are fully considered, well focused, resilient, practical and cost-effective. You will also ensure that you learn from any mistakes you make, and feed this back into future planning and Decision Making.
Once you have devised a plan you should evaluate whether it is likely to succeed. This evaluation may be cost or number based, or may use other analytical tools. This analysis may show that your plan may cause unwanted consequences, may cost too much, or may simply not work. In this case you should cycle back to an earlier stage. Finally, you should feed back what you have learned with one plan into the next through a review or evaluation process
The Steps are listed below and described in more detail in the sections that follow:
- Step 1 Building the evidence base
- Step 2 Stakeholder analysis
- Step 3 Problem and option analysis
- Step 4 Option analysis and strategy formulation
- Step 5 Intervention logic – going from themes to activities
- Step 6 Adding indicators, setting targets and working out means of verification
- Step 7 Risks and assumptions
- Step 8 Bringing it all together and achieving coherence by using an adapted logical framework
- Step 9 Formal signing of the inclusion framework by all the partners
Step 1: Building the evidence base
Purpose of the step: to find evidence to find out what is happening to target groups affected by the problems
Main technique: desk research
This phase involves desk research to find out as much as possible about the nature of the problems facing the target groups that you are thinking of tackling.
Policy mapping: Identify what agencies are already doing to address the problems and map it out to look at coverage. Policy mapping needs to identify all the actions by possible stakeholders that affect the situation of target groups. These actions may be quite tangential. For example in a strategy to increase school staying on rates it may be important to look at private and public sector recruitment practices. Young people may be leaving because they think that qualifications will make no difference in a labour market where discrimination is not curbed.
Identify what is working and what is not working:Much delivery focuses on doing the things that have always been done. The discussion with partners works much better if there is some externally generated evidence (for example evaluations or reviews) that inform discussion and provide an evidence base so that criticism is not seen as one person’s opinion but is firmly rooted. It is also helpful to map the level of coverage of existing actions. Often there are good practices but they only operate for some communities or as pilot projects. If possible the cost of different approaches should be identified.
Summary of key questions to help build the evidence base:
- What does the quantitative evidence base suggest have been the trends of the relevant target groups in relation to social exclusion in your local area or region over the past few years and beyond?
- What appears to be the nature of the social exclusion in your local area?
How does your chosen goal represent an opportunity for tackling this form of exclusion?
- What are the barriers (or market failures) underlying these trends that are holding back the target groups in your local area or region?
- What previous policy efforts have been tried and tested? Which did and did not work and why?
Step 2: Stakeholder analysis
Purpose of the step: to identify who the stakeholders are and what are there interests Techniques: desk research and analysis
Stakeholders can be defined as all those that have an interest (or stake) in an activity, project or programme – in our case the action plan. This includes intended beneficiaries, and intermediaries, winners and losers and those involved or excluded in the decision making process (DFID 2004).
Stakeholders are frequently divided into primary stakeholders who are affected by the policy – either positively or negatively and secondary stakeholders – those that have an intermediary role including delivery agencies, policy makers, and field workers. Some versions limit the number by defining some of each group as Key stakeholders otherwise the potential numbers can be limitless.
Stakeholders have different interests so it is useful to define what their involvement is with the project and how their interests differ. By systematically analysing the stakeholders it is also possible to see whether there are any missing voices. The exclusion of the client group is perhaps the most frequent missed voice. It is also important to assess the capacity of different stakeholders to engage in the process. A common failure of consultation exercises is to assume that one size fits all and fail to adapt approaches to particular groups. For example the private sector finds very long agendas and meetings frustrating and attendance drops away. Women are often not consulted even when the subject is highly relevant to them Sometimes special meetings are necessary to capture the voice of a particular group. Table 3 below sets out a format for analysing different stakeholder interests.
There is a good discussion of stakeholder analysis at a UK site for the department of International Development http://www.dfid.gov.uk/pubs/files/toolsfordevelopment.pdf
Step 3 Problem analysis
Purpose: to identify all the problems and the way that they are linked to causes and effects
Techniques: Summarise evidence from step 1 followed by stakeholder meetings and analysis (stakeholder meeting may be combined with step 4)
The Local Action Plan should include a clear outline of the nature and scale of the problem in the Local Action Plan area. A fresh and comprehensive understanding of the existing situation and the problems that exist is essential to enabling the right solutions to be found.
Stakeholder involvement in this stage will expand the way that the problem is perceived and ensure that problems are not merely ‘agency’ views. It is particularly important to involve the users or beneficiaries (the primary stakeholders) in problem and needs analysis.
The action plan needs to recognise that problems facing the groups are complex, intractable and inter-connected. No simple solutions are likely to work and ‘business as usual’ approaches by existing agencies need to be challenged because it is the nature of the problems facing the groups combined with the inadequacy of social policy responses that have created the problems found today.
There are many different ways of viewing the same problem. Depending on the perspective different solutions will be deployed. The choice between different options is assisted by research evidence.
One well established technique for working with problems in a group setting is to make a problem tree. This is a simple graphical representation of the problems, their causes and effects.
Stages in drawing up a problem tree:
- List all the problems that come to mind. Problems need to be carefully identified: they should be existing problems, not possible, imagined or future ones. The problem is an existing negative situation, it is not the absence of a solution
- Identify a core problem (this may involve considerable trial and error before settling on one).
- Determine which problems are “Causes” and which are “Effects.”
- Arrange in hierarchy both Causes and Effects, i.e., how do the causes relate to each other - which leads to the other, etc.
Bring evidence to the stakeholder meeting
Understanding the problem needs evidence to inform the discussion. This evidence can be from statistics and studies that you have commissioned and collected at the start of the work in step 1. There may be a need to commission fresh research, although the long lead times for research may make this unfeasible. Normally it is best to commission an outside consultant or one of the partners to do a quick review of available and relevant published studies and ‘grey’ literature – reports that have not been published.
It is also useful to analyse data on the problem and to look at existing data in new ways – for example by breaking it down into small spatial units to see where the problems are concentrated geographically. Data should also be presented to illustrate the relationships with demographic characteristics, economic circumstances and other issues that affect the target groups.
Step 4 Option analysis and strategy formulation
Purpose: to identify the different strategy options that may be available and then to make choices between them in order to fix on a strategy. Techniques: Stakeholder meetings and analysis (stakeholder meeting may be combined with step 3) Be explicit about the options available.
Strategy development involves making choices between options. Even if the only counter example is the ‘do nothing’ option or retain the status quo. It helps in drawing up the action plan to be explicit about policy options and to look for evidence based ways to select between them. However, it should be noted that the evidence-based approach is often better at rejecting options than selecting them.
A range of solutions can solve any problem. For example reducing unemployment can be addressed by increasing the ‘employability’ of the unemployed, and/or by creating jobs for people to go into. Often a combination of different supply side and demand side measures are needed to create long-term change.
Strategy is about deciding the particular policy mix and balance of resources that best addresses the problems in a particular area. Sometimes less is more – concentrating resources on a few effective actions is better than spreading the jam too thinly by supporting too many under funded initiatives. Many partnership based strategies fall into the trap of doing too much and supporting too many actions by trying to satisfy all the stakeholders. This is a particular risk in partnerships where the strongest partners are horizontal stakeholders that supply of services to the target groups and have a vested interest to use the action plan to lever resources.
Examine research and good practice to find out what has worked elsewhere
Because urban problems is so intractable fresh ideas are needed to tackle it. There is some truth in the adage ‘there is nothing new under the sun’ Most solutions have been tried somewhere – sometimes in other parts of Europe sometimes in the USA or the developing world. These approaches should be examined and where appropriate adapted for use in your locality or region
Step 5 Intervention logic – going from goals to actions
Purpose: to work on the goals, objectives, outputs and activities of the action plan and to ensure that the intervention logic connecting them is explicit and clear.
Techniques: This step is best done with the stakeholders in a facilitated meeting
The step is set out in four sections:
a) From themes to Objectives
b) From Objectives to Outputs
c) From Outputs to Activities
d) Activities
a) From themes to Objectives
The next stage is to define an objective that the action plan will focus on. The Objective should be achievable over a known time period. It will be a more limited and more specific version of the theme. One way of thinking about the Objective is to vision the changed situation that you would wish to see at a future time. We suggest that the plan should focus on a 5-year time horizon but you can make it longer. The Objective may also be more specific, for example by only focusing on one target group or on one service.
b) From Objectives to Outputs
Here we focus on what outputs need to be delivered by the action plan partnership in order to deliver the objective. In our child poverty example the outputs could be achieved by raising of parental incomes as a result of helping single parents into work and ensuring that the tax and benefit system supports this move. Some changes might be outside the control of the action plan partnership – for example tax changes by central government. These will be built into the plan later as assumptions and risks.
c) From Outputs to activities
The final stage moves us from outputs (what we want to achieve) to activities (how we will achieve the outputs). This is the crucial place where incoherence can creep into plans as partners try to ensure that their projects are included as activities regardless of whether they contribute to critical outputs. Activities that do not contribute to outputs can be excluded or revised now or later when the indicators are drawn up.
d) Defining activities
The key is to ask what activity is required to deliver each output
Working out the actions to be pursued is not entirely a top down activity. Partners have ideas about the activities that they wish to pursue in order to meet the action plan objective. What is needed is an iterative and at times negotiated process to bring appropriate activities into the activities table while excluding those that do not make significant contributions to the objective. An activities table is set out below in table 7 below:
Step 6 Adding indicators, means of verification and setting targets
Purpose: to add indicators, means of verification and set realistic targets to be achieved
Techniques: The development of indicators is a technical task carried out by analysts in close consultation with stakeholders
The next step is to attach indicators to the objective, outputs and activities. As well as identifying the indicators the sources of data to verify that the target has been reached are also identified in the third column: means of verification
In general we would suggest using local data where available as this may have shorter time lags to publication than national data as well as being more suited to the local objectives. Where possible it is best to adapt existing data collection systems that agencies. However some one-off surveys carried out by research institutes or foundations may be necessary despite being expensive to implement.
Our suggestion is that for the Action Plan objective and the outputs you identify indicators and means of verification. This means that you do not need to work on indicators at the level of themes or activities.
For each indicator you should identify sources of information that enable you to verify that the Objective has been achieved or that the outputs have been delivered. The table below summarises what the indicators are trying to do.
Quantifying the indicators
Once the indicators and means of verification have been defined and agreed the next stage is to quantify the indicators and decide how much progress the plan aims to achieve. These are the explicit quantitative or qualitative achievements to be achieved by the action plan. They should be achievable but challenging at the same time. There is a danger with quantified indicators, which is that they can induce ‘perverse’ behaviour. For example in the UK in order to achieve a government target for family doctors of seeing 80% of patients within 2 days of seeking an appointment some doctors surgeries refused to allow patients to book appointments more than 2 days in advance. This was inconvenient for patients that had to work and organise appointments around a busy schedule.
In some policy areas quantified indicators can be very political. Setting an over ambitious target and then failing to achieve it can have serious effects.
You may wish to relate the quantified indicators to ‘reference targets’ that appear in some NAPs Inclusion at national level.
Summary on indicators and methods of verification
Indicators are essential but painful. The advantage of the indicator matrix is that it forces you to link your indicators to your intervention logic. At the same time it allows considerable freedom to select indicators that are relevant to what you want to measure
- Use as few indicators as possible – they are expensive to collect and process.
- Use a variety of indicator types and remember to measure quantitative and qualitative change – qualitative change can be more useful
- Find indicators that relate directly to the outputs and objectives, this will often mean creating local indicators
Step 7 Risks and assumptions
Purpose: to identify the risks that may affect the action plan and the assumptions on which the plan depends
Techniques: Analysis checked in consultation with the key stakeholders
Action plan partners can only control their own behaviour. Inevitably the action plan is at risk from other partners not delivering, from changes in the external environment including other higher levels of government making changes that worsen conditions for the target groups. An example of an external risk would be where refugee status is changed so that social security benefits, the right to work or the right to remain in the country are weakened. This would be a national change that would impact negatively on the position of refugees in a local community.
It is possible to identify three types of risk
- Internal risks that you can control (e.g.design, management systems, performance)
- External risks others control (e.g. national legislation)
- External risks no one controls (e.g. natural disasters)
Key questions to uncover the assumptions
If the partnership successfully delivers all of the activities what are the assumptions about external risks that need to be made if the outputs are to be delivered?
If the partnership successfully delivers all of the outputs what assumptions about external risks need to be made if the objective is to be delivered?
Risk management
Identifying the assumptions on which the action plan depends is a passive exercise. The next step is to identify whether some of these risks can be managed. In risk management there are three ways of handling risk:
- Risks are transferred – this can be done by forms of insurance – so that another agency bears the risk (insuring parties against rain is a common way of dealing with bad weather in the UK)
- Risks are tolerated - if it is difficult to do anything about the risk, then it may be best to take no action – especially if the cost of action is disproportionate
- Risks are treated - usually the intention is to contain the risk at an appropriate level.
Step 8 Bringing it all together and achieving coherence by using an adapted logical framework
Purpose: to ensure that the action plan is coherent – i.e. that the actions will lead to the outputs, the outputs will lead to the objectives and the objectives support the theme
Techniques: This can be done either as a technical exercise or as a participative exercise with the stakeholders.
The final act is to assemble all the parts that you have been working on above and put them together in a single matrix, which is called the Logical framework.
The table below shows a Logical framework or log frame that has been adapted for use with an action plan containing a number of activities rather than for a single project. Log frames are helpful in developing action plans that are coherent with their objectives. However, the traditional approach can be daunting for a group that is not trained in their use.
If you have gone through all the steps above then you can combine all of it into a single log frame that looks like the one in table 11 below.
Table 11 Adapted version of Logical framework table for URBACT 2 Local Action Plans
Step 9 Signing the Accord
Purpose: to signal to the outside world that the action plan has been agreed at high level, to gain publicity
Techniques: Hold a reception and invite the 360 degree stakeholders that have contributed to the plan
It is important that the completed plan should be signed off at the highest level by the partners involved. This event should be high profile and include a press release and an appropriate ceremony and reception.